Legislation Details

File #: 26-7034    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 10/13/2026 In control: Commissioners Court
On agenda: 10/29/2026 Final action: 10/29/2026
Title: Request for approval of a change in contract with MC2 Civil, LLC, in connection with final construction of Roadway Maintenance - Asphalt Package - 2 - 2025, adding 9 calendar days, with a deduction in the amount of $871,938.69, Job No. 25/0419-1, UPIN 25103MF3MW01, Precinct 3, MWBE Contracted Goal: 30.33%, MWBE Current Participation: 46.18%.
/
Harris County Commissioners Court
Request for Court Action
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 25/0419, UPIN 25103MF3MW01
Vendor/Entity Legal Name (if applicable): MC2 Civil, LLC

MWBE Contracted Goal (if applicable): 30.33%
MWBE Current Participation (if applicable): 46.18%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with MC2 Civil, LLC, in connection with final construction of Roadway Maintenance - Asphalt Package - 2 - 2025, adding 9 calendar days, with a deduction in the amount of $871,938.69, Job No. 25/0419-1, UPIN 25103MF3MW01, Precinct 3, MWBE Contracted Goal: 30.33%, MWBE Current Participation: 46.18%.
end

Background and Discussion:
This project consists of base repair, milling and overlay, striping, and traffic signal loop improvements along Hargrave Road from SH 249 to Falba Road, approximately 5,200 feet (0.99 miles), and along Dowdell Road from Kuykendahl Road to FM 2920, approximately 9,900 feet (1.9 miles).

This change in Contract includes:
(PCO #1, RFI #4) MC2 is requesting a 9-calendar-day contract extension with no additional compensation. The request is primarily due to multiple rain-out days during the 47-day contract period, as well as schedule impacts from performing concurrent roadway and driveway work.

Expected Impact:
The expected impact is to reconcile the contract time with documented project delays and provide the additional time that was necessary to complete the remaining work.

...