File #: 26-7031    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 10/13/2026 In control: Commissioners Court
On agenda: 10/29/2026 Final action: 10/29/2026
Title: Request for approval of a change in contract with Environmental Allies Inc., in connection with final construction of Park and Road Improvements - Eisenhower Park – 2024, adding 34 calendar days, with an addition in the amount of $55,924.25, Job No. 25/0409-1, UPIN 25101MF3RN01, Precinct 1, MWBE Contracted Goal: 17.04%, MWBE Current Participation: 4.14%.
Sponsors: Mony Hossain
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: Commissioner, Precinct 1
Secondary Department Head/Elected Official: Rodney Ellis

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 25/0409, UPIN 25101MF3RN01
Vendor/Entity Legal Name (if applicable): Environmental Allies Inc.

MWBE Contracted Goal (if applicable): 17.04%
MWBE Current Participation (if applicable): 4.14%
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Environmental Allies Inc., in connection with final construction of Park and Road Improvements - Eisenhower Park – 2024, adding 34 calendar days, with an addition in the amount of $55,924.25, Job No. 25/0409-1, UPIN 25101MF3RN01, Precinct 1, MWBE Contracted Goal: 17.04%, MWBE Current Participation: 4.14%.
end

Background and Discussion:
The project consists of roadway reconstruction and drainage improvements within Eisenhower Park in Harris County Precinct 1. The purpose of the project is to enhance public safety and improve the overall quality of life by rehabilitating the existing roadway pavement and upgrading the drainage infrastructure. These improvements will provide better driving conditions, improve pedestrian safety, and mitigate drainage issues for residents and park visitors.

The change in contract includes the following:

The line items are adjusted to reconcile overrun, underrun quantities and add new line items on the project for completion of the proposed scope of work.

The increase in quantities due to overruns of existing line item numbers 5, 6, 9, 10, 13, 15, 16, 17, 18, 19, 20, 22, 26, 32, 33...