File #: 26-7009    Version: 1 Name:
Type: Investment Memo Status: Agenda Ready
File created: 10/7/2026 In control: Commissioners Court
On agenda: 10/15/2026 Final action:
Title: Request by Universal Services for approval of a Final Investment Memo for the Electronic Document Management project for a total authorization of 1,860,000 for FY2027 and request for commercial paper funding in the amount of $1,860,000.
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Primary Department: Universal Services
Primary Department Head/Elected Official: Sindhu Menon, Executive Director & CIO

Managing Department: Universal Services
Managing Department Head/Elected Official: Sindhu Menon, Executive Director & CIO

Regular or Supplemental RCA: Supplemental RCA
Type of Request: Investment Memo
Investment Memo Type: Final Investment Memo

Project Name: Electronic Document Management
Project ID (if applicable): NI037
Vendor Legal Name (if applicable): N/A

MWBE Contracted Goal (if applicable): N/A
MWBE Current Achievement (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Incremental Authorization Requested: $1,860,000
Total Estimated Project Cost: $3,720,000 (FY27+FY28)

Request Summary:
title
Request by Universal Services for approval of a Final Investment Memo for the Electronic Document Management project for a total authorization of 1,860,000 for FY2027 and request for commercial paper funding in the amount of $1,860,000.
end

Project Description:
The FY2027 goals are:
Modernize the County's enterprise document management platform by migrating from on-premises to cloud, completing the capture platform transition, and building internal delivery capacity to reduce long-term vendor dependency.

Anticipated Project Expenditures and Timeline:
Project Scope Breakdown
Estimated Cost
Estimated Completion

3 FTE’s - 1 Developer, 2 Analysts
$438,400
09/30/2027

Contract Staff
$616,480
09/30/2027

Vendor Cloud Professional Services - Moving the application to the cloud
$260,000
09/30/2027

Vendor Project Services – Contractors for implementation of new OpenText flows and enhancements to existing applications
$300,000
09/30/2027

Contingency
$245,120
09/30/2026

FY27 Total Authorization
$1,860,000



Justification & Alterna...