Primary Department: Flood Control District
Primary Department Head/Elected Official: Marcus Y. Stuckett, P.E., CFM
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Supplemental RCA
Type of Request: Contract - Award
Project ID (if applicable): N100-00-00-E004
Vendor/Entity Legal Name (if applicable): Texas Water Development Board (TWDB)
MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): HCFCD, HCTRA, HHS
Request Summary (Agenda Caption):
title
Request by the Flood Control District for approval of a grant agreement with Texas Water Development Board, in the amount of $11,000,000, to fund the Cloverleaf Area Drainage Improvements in the Carpenters Bayou Watershed (Bond ID Z-02, Project ID N100-00-00-E004, Agreement No. 2026-115, Precinct 2).
end
Background and Discussion:
This agreement will fund the Cloverleaf Area Drainage Improvements in the Carpenters Bayou Watershed. The 89th Texas Legislature allocated funds in Senate Bill 1 to the Harris County Flood Control District. Senate Bill 1 was signed by the Governor on June 22, 2025, and will be effective on September 1, 2025. This allocation from the Texas Legislature is being obtained through the Texas Water Development Board. The project in Senate Bill 1 is the Carpenters Bayou Watershed Improvements.
Expected Impact:
This agreement will fund construction of the recommended detention mitigation solution. The Cloverleaf Area Drainage Improvements Project will improve the internal drainage systems and related infrastructure that convey stormwater from the Cloverleaf subdivision to Carpenters Bayou. As part of the project, roadside drainage ditches in the neighborhood will be desilted, regraded, and/or resized to increas...