Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 23/0230, UPIN 161033020711
Vendor/Entity Legal Name (if applicable): Brice Construction & Design LLC
MWBE Contracted Goal (if applicable): 27.56%
MWBE Current Participation (if applicable): 62.79%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Brice Construction & Design LLC, in connection with final construction of Mueschke 8; 2,700' south of Draper Road to approximately 500' north of Draper Road, adding 400 calendar days, with an addition in the amount of $163,586.44, Job No. 23/0230-2, UPIN 161033020711, Precinct 4, MWBE Contracted Goal: 27.56%, MWBE Current Participation: 62.79%.
end
Background and Discussion:
This project consists of widening an existing two-lane concrete roadway into a standard four-lane boulevard, including associated drainage improvements connecting to both Mueschke 7 and Mueschke 9. The project limits extend from approximately 2,700 feet south of Draper Road to approximately 500 feet north of Draper Road. The project was administered by the Office of the County Engineer.
Added Items:
PCO #5 - Contract Time Extension
Four hundred (400) Additional days are required due to the lead time needed for the Precinct to review and approve recommendations necessary to complete the punch list items.
Cost: $0.00 Time: 400 Days
PCO #7 - Final Adjustment for reconciliation of actual quantities used during construction.
Cost: ...