Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E, PMP, CFM, ENV SP, County Engineer
Secondary Department: Commissioner, Precinct 1
Secondary Department Head/Elected Official: Commissioner Rodney Ellis
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): UPIN 20101MF1JC01
Vendor/Entity Legal Name (if applicable): CONSOR North America, Inc.
MWBE Contracted Goal (if applicable): 0%
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with CONSOR North America, Inc., in the amount of $104,213.00 for Construction Phase Engineering Services in connection with Hike and Bike Trail - CE King - 2020, UPIN 20101MF1JC01, Precinct 1.
end
Background and Discussion:
The project is to construct approximately 2.2 miles of 12-foot wide, 6-in thick concrete bike trail along east side of CE King Parkway from Tidwell Road to Garrett Road. The project also includes a three-span pedestrian bridge at HCFCD Channel P121-00-00.
Expected Impact:
The project will provide safe pedestrian and bike routes along CE King Parkway.
Alternative Options:
If no action is taken, the engineer of record will not be accessible for support through the construction of the project.
County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: F: Ensure safety and security for all using the county’s transportation network in alignment with the County’s Vision Zero plan.
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): F1: Stre...