Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: Commissioner, Precinct 3
Secondary Department Head/Elected Official: Tom Ramsey
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 25/0079, UPIN 23103MF2VT01
Vendor/Entity Legal Name (if applicable): LMC Corporation
MWBE Contracted Goal (if applicable): 21.98%
MWBE Current Participation (if applicable): 81.54%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with LMC Corporation, in connection with Wastewater System Rehabilitation - Spring Camp and Klein Park, adding 7 calendar days, with an addition in the amount of $26,154.80, Job No. 25/0079-2, UPIN 23103MF2VT01, Precinct 3, MWBE Contracted Goal: 21.98%, MWBE Current Participation: 81.54%.
end
Background and Discussion:
Project included the Wastewater System Rehabilitation - Spring Camp and Klein Park. This change order is necessary to compensate the Contractor for unforeseen concrete and damaged piping encountered during sewer line replacement, the addition of a sliding gate to the project scope and raising the existing manhole to finished grade to eliminate water ponding, address safety concerns, and maintain proper utility access and compliance. This change in contractor allows the contractor to be properly compensated for the additional work and time.
This change includes these new bid items:
Additional Sewer Line and concrete removal LS $10,606.80
Fabrication and installation of cantilever sliding gate EA $4,823.00
Lift Station adjustment and concrete removal around it LS $10,725.00
Expected Impact:
This chang...
Click here for full text