Legislation Details

File #: 26-6525    Version: 1 Name:
Type: Contract - Amendment Status: Agenda Ready
File created: 9/29/2026 In control: Commissioners Court
On agenda: 10/15/2026 Final action:
Title: Request for approval of a change in contract with CE Barker, LTD, in connection with Sanitary Sewer System Construction - Westfield Estates - 2023, with an addition in the amount of $482,579.10, Job No. 24/0313-5, UPIN 23208MF2XZ01, Precinct 2, MWBE Contracted Goal: 19.82%, MWBE Current Participation: 35.51%.
Sponsors: Mony Hossain
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 24/0313, UPIN 23208MF2XZ01
Vendor/Entity Legal Name (if applicable): CE Barker, LTD

MWBE Contracted Goal (if applicable): 19.82%
MWBE Current Participation (if applicable): 35.51%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with CE Barker, LTD, in connection with Sanitary Sewer System Construction - Westfield Estates - 2023, with an addition in the amount of $482,579.10, Job No. 24/0313-5, UPIN 23208MF2XZ01, Precinct 2, MWBE Contracted Goal: 19.82%, MWBE Current Participation: 35.51%.
end

Background and Discussion:
Harris County Office of the County Engineer received American Rescue Plan Act (ARPA) funding for wastewater and water projects. Through a vetting process, the Westfield Estates Sanitary Sewer System project was selected. The project scope includes sanitary sewer lines, manholes, a lift station and a force main, as well as connecting properties to the new system and abandoning existing septic systems. This initiative addresses environmental concerns by replacing failing septic systems that risk contaminating roadside ditches and nearby waterways.
This Change Order is tied to PCO-8 & PCO-9 (Overrun QTY): PCO-8: This Proposed Change Order provides an additional 30 LF of 4-inch sanitary sewer lead required to complete the intended sewer connection at the Tire Shop located at 11002 Aldine Westfield. Plan Sheet 93 identifies 2115 Kowis Street as the last property...