Legislation Details

File #: 26-6388    Version: 1 Name:
Type: Investment Memo Status: Agenda Ready
File created: 9/11/2026 In control: Commissioners Court
On agenda: 9/22/2026 Final action:
Title: Request for approval of a Final Investment Memo for the Elevator Repair and Renovations projects, for an incremental amount of $4,980,000 for a total authorization of $6,280,000 for FY 2027.  
Sponsors: Mony Hossain
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer

Managing Department: County Engineer
Managing Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer

Regular or Supplemental RCA: Regular RCA
Type of Request: Investment Memo
Investment Memo Type: Final Investment Memo

Project Name: Elevator Repair and Renovations
Project ID (if applicable): MF0ELEVATORS
Vendor Legal Name (if applicable): N/A

MWBE Contracted Goal (if applicable): N/A
MWBE Current Achievement (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Incremental Authorization Requested: $4,980,000
Total Estimated Project Cost: $18,653,000 (FY 2027-31)

Request Summary:
title
Request for approval of a Final Investment Memo for the Elevator Repair and Renovations projects, for an incremental amount of $4,980,000 for a total authorization of $6,280,000 for FY 2027.  
end

Project Description:
This is a continuous lifecycle management project to identify and address all required upgrades and modernization of elevators, escalators, lifts, related equipment, and infrastructure in County Facilities. This project addresses elevator equipment in multiple County facilities that are outdated and where replacement parts are not readily available and, in some cases, no longer available.
Below are the planned allocations; there might be changes in the County’s needs that result in minor operational changes and funding for the projects throughout the Fiscal Year. The County Engineer is authorized to adjust scope and projects at their discretion within the program. Any additional financial authorizations would go through Commissioners Court approval.
Anticipated Project Expenditures and Timeline:
Project Scope Breakdown
...

Click here for full text