Legislation Details

File #: 26-6340    Version: 1 Name:
Type: Contract - Amendment Status: Agenda Ready
File created: 9/10/2026 In control: Commissioners Court
On agenda: 9/22/2026 Final action:
Title: Request for approval of change in contract No. 7 with Lecon, Inc., for Major Maintenance of Cypress Creek and Tributaries Batch 4, adding 26 calendar days (Cypress Creek Watershed, Bond ID CI-012, Project ID K100-00-00-X110, Job No. 23/0237, Precinct 3, MWBE Contracted Goal: 21%, MWBE Current Participation: 16.82%).
Attachments: 1. 092226 CIC LECON K100-X110 PCT 3 backup.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Primary Department: Flood Control District
Primary Department Head/Elected Official: Marcus Y. Stuckett, P.E., CFM

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): K100-00-00-X110
Vendor/Entity Legal Name (if applicable): Lecon, Inc.

MWBE Contracted Goal (if applicable): 21%
MWBE Current Participation (if applicable): 16.82%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of change in contract No. 7 with Lecon, Inc., for Major Maintenance of Cypress Creek and Tributaries Batch 4, adding 26 calendar days (Cypress Creek Watershed, Bond ID CI-012, Project ID K100-00-00-X110, Job No. 23/0237, Precinct 3, MWBE Contracted Goal: 21%, MWBE Current Participation: 16.82%).
end

Background and Discussion:
This change in contract is needed to complete the construction contract for this project. Major Maintenance of Cypress Creek and Tributaries, Batch 4 includes restoring eight tributary channels by replacing failed outfall pipes, removing accumulated sediment, and repairing areas where erosion and infrastructure damage occurred during the Harvey and Memorial Day storms. The purpose of this contract change is to extend the contract time due to inclement weather. The contract change includes $0 and 26 days.

Expected Impact:
This change will allow the contractor to construct the project so that Harris County can realize intended flood risk reduction benefits.

Alternative Options:
This is an active construction contract, so there are not many alternatives to approving a change order other than cancelling the contract, which is not recommended as doing so would substantially delay the remaining work in ...

Click here for full text