Legislation Details

File #: 26-6281    Version: 1 Name:
Type: Contract - Amendment Status: Agenda Ready
File created: 9/9/2026 In control: Commissioners Court
On agenda: 9/22/2026 Final action:
Title: Request for approval of a change in contract with Millis Equipment, LLC, in connection with final construction of Hufsmith-Kohrville Rd 2, with a deduction in the amount of $1,577,806.51, Job No. 23/0308-7, UPIN 15104M23NP02, Precinct 3, MWBE Contracted Goal: 28.50%, MWBE Current Participation: 30.95%.
Sponsors: Mony Hossain
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 23/0308, UPIN 15104M23NP02
Vendor/Entity Legal Name (if applicable): Millis Equipment, LLC

MWBE Contracted Goal (if applicable): 28.50%
MWBE Current Participation (if applicable): 30.95%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Millis Equipment, LLC, in connection with final construction of Hufsmith-Kohrville Rd 2, with a deduction in the amount of $1,577,806.51, Job No. 23/0308-7, UPIN 15104M23NP02, Precinct 3, MWBE Contracted Goal: 28.50%, MWBE Current Participation: 30.95%.
end

Background and Discussion:

Project included the reconstruction of Hufsmith-Kohrville Road from Hollow Glen Lane to 500' North of Ezekiel from 2 lane asphalt road to 4 lane concrete curb and gutter boulevard with 32' raised median with traffic signals at Lacey Road and Ezekiel Road. There are two outfalls within limits of the project, North Pointe Boulevard and Champion Wood Drive detention ponds. The requested change order is necessary to compensate the contractor for additional scope. These changes materially altered the original scope, cost, and schedule, warranting appropriate contract adjustment.

The change in contract includes the following:
The final adjustment (reconciliation of actual quantities used in construction against the bid
quantities). -$1,577,806.51).



Expected Impact:
This change will allow the Contractor to be properly compensated for the additional work.

Al...