Legislation Details

File #: 26-6280    Version: 1 Name:
Type: Contract - Amendment Status: Agenda Ready
File created: 9/9/2026 In control: Commissioners Court
On agenda: 9/22/2026 Final action:
Title: Request for approval of a change in contract with Durwood Greene Construction Co. in connection with final construction of Asphalt Rehabilitation – Memorial Drive between San Felipe and West of Chimney Rock - 2024, with a deduction in the amount of $550,068.56, Job No. 25/0302-1, UPIN 25103MF3MT01, Precinct 3, MWBE Contracted Goal: 31.56%, MWBE Current Participation: 50.88%.
Sponsors: Mony Hossain
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 25/0302, UPIN 25103MF3MT01
Vendor/Entity Legal Name (if applicable): Durwood Greene Construction Co.

MWBE Contracted Goal (if applicable): 31.56%
MWBE Current Participation (if applicable): 50.88%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Durwood Greene Construction Co. in connection with final construction of Asphalt Rehabilitation – Memorial Drive between San Felipe and West of Chimney Rock - 2024, with a deduction in the amount of $550,068.56, Job No. 25/0302-1, UPIN 25103MF3MT01, Precinct 3, MWBE Contracted Goal: 31.56%, MWBE Current Participation: 50.88%.
end

Background and Discussion:
Project included the Mill and overlay, with base repairs and updates pavement markings, of approximately 2.7 miles of Memorial Drive, between San Felipe and West of Chimney Rock Road. The requested change order is necessary to compensate the contractor for additional scope. These changes materially altered the original scope, cost, and schedule, warranting appropriate contract adjustment.

The change in contract includes the following:
The final adjustment (reconciliation of actual quantities used in construction against the bid
quantities). -$550,068.56.

Expected Impact:
This change will allow the Contractor to be properly compensated for the additional work.


Alternative Options:
Conduct thorough pre-construction assessments and detailed utility mapping to identify and ...

Click here for full text