Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No: 25/0046, UPIN 22101MF2F801
Vendor/Entity Legal Name (if applicable): Spawglass Construction Corp.
MWBE Contracted Goal (if applicable): 25.09%
MWBE Current Participation (if applicable): 25.53%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Spawglass Construction Corp. in connection with Connectivity Project – Deussen-Eisenhower – 2021, with an addition in the amount of $40,974.67, Job No. 25/0046-10, UPIN 22101MF2F801, Precinct 1, MWBE Contracted Goal: 25.09%, MWBE Current Participation: 25.53%.
end
Background and Discussion:
The project is to construct waterfront structures, pedestrian bridges, parking lot, boardwalk, trail, parking lot, lighting and landscape in both Alexander Deussen and Dwight D. Eisenhower Parks. The County issued the Project’s Notice to Proceed on July 14, 2025. Per Attachment M of the Contract, the work was to be completed within 840 days of the Notice to Proceed, or by October 31, 2027. With this and all other prior approved change orders, the work is to be completed within 890 days of the Notice to Proceed, or by December 21, 2027.
Expected Impact:
This project will provide the community with improved park amenities and features.
Alternative Options:
If no action is taken, needed park improvements will not be achieved to serve the communities.
County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed...
Click here for full text