Title: Request for approval of a Preliminary Investment Memo for the JD Walker Community Center Renovation project for an initial amount of $790,000 and request for authorization and commercial paper reallocation from the Leon Grayson/Baldree Community Center Renovation project in the amount of $790,000.
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Primary Department: Commissioner, Precinct 2
Primary Department Head/Elected Official: Commissioner Adrian Garcia

Managing Department: Commissioner, Precinct 2
Managing Department Head/Elected Official: Commissioner Adrian Garcia

Regular or Supplemental RCA: Regular RCA
Type of Request: Investment Memo
Investment Memo Type: Preliminary Investment Memo

Project Name: JD Walker Community Center Renovation
Project ID (if applicable): TBD
Vendor Legal Name (if applicable): TBD

MWBE Contracted Goal (if applicable): N/A
MWBE Current Achievement (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Incremental Authorization Requested: $790,000
Total Estimated Project Cost: $10,790,000

Request Summary:
title
Request for approval of a Preliminary Investment Memo for the JD Walker Community Center Renovation project for an initial amount of $790,000 and request for authorization and commercial paper reallocation from the Leon Grayson/Baldree Community Center Renovation project in the amount of $790,000.
end




Project Description:
The JD Walker Community Center Renovation project will modernize and rehabilitate the existing 19,000 square foot facility and include the construction of an approximately 3,500 square foot addition to accommodate a new workout and fitness area. The renovation will enhance the center’s functionality and create a more comprehensive community-focused space.
The project scope includes programming and design services, appliance upgrades, landscaping improvements, HVAC system enhancements, and interior and exterior lighting upgrades. A complete roof replacement is also planned. In addition, a parking study will be conducted to assess current capacity and determine future parking requirements.
Anticipated Project Expenditures and Timeline: