Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E, PMP, CFM, ENV SP, County Engineer
Secondary Department: Commissioner, Precinct 1
Secondary Department Head/Elected Official: Rodney Ellis, Commissioner
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): UPIN 26101EWW7B01
Vendor/Entity Legal Name (if applicable): Civitas Engineering Group, Inc.
MWBE Contracted Goal (if applicable): 19%
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with Civitas Engineering Group, Inc. in the amount of $2,431,469.00 for Professional Engineering Services in connection with Road Improvements - Antoine Drive - W Mt Houston to Tomball Parkway, UPIN 26101EWW7B01, Precinct 1, MWBE Contracted Goal: 19%.
end
Background and Discussion:
Antoine Drive from W Mount Houston to Tomball Parkway is an existing four-lane concrete boulevard. This segment is to be reconstructed to accommodate 10’ shared use path on both sides of the roadway.
Expected Impact:
Reconstructed boulevard segment to include 10’ shared use path on both sides of Antoine Drive within project limits.
Alternative Options:
No alternative options. If not approved, the design will be delayed or cancelled.
County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): F1: Strengthen the County’s commitment to Vision Zero pri...