Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 25/0194, UPIN 19101MF14G01
Vendor/Entity Legal Name (if applicable): SER Construction Partners LLC
MWBE Contracted Goal (if applicable): 32.17%
MWBE Current Participation (if applicable): 56.54%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with SER Construction Partners, LLC, in connection with Houmont Park Subdivision Drainage Improvements - 2018, adding 4 calendar days, with an addition in the amount of $16,063.25, Job No. 25/0194-3, HC Road Fund, UPIN 19101MF14G01, Precinct 1, MWBE Contracted Goal: 32.17%, MWBE Current Participation: 56.54%.
end
Background and Discussion:
The Houmont Park Subdivision Drainage Improvements - HCFCD Unit No. P110-04-00 & P110-00-00 project site consists of subdivision drainage and roadway improvements located between C E King Parkway and Van Hut Lane. The project includes roadside ditch improvements along Unison Rd and Ticonderoga Rd and channel improvements on P110-04-00 and P110-00-00. Two detention basins will be excavated to mitigate for the conveyance improvements for this project.
The change in contract includes the following:
The line items are adjusted to reconcile overrun quantities and add new line items to the project for completion of the proposed scope of work.
The increase in quantities on overrun line item number 121 for an addition in the amount of $13,740.25 and zero (0) days.
Added new line item needed to complete the ...