Legislation Details

File #: 26-5908    Version: 1 Name:
Type: Transmittal Status: Agenda Ready
File created: 9/2/2026 In control: Commissioners Court
On agenda: 9/17/2026 Final action:
Title: Transmittal by the Office of the County Engineer of a substantial completion certificate with Brice Construction and Design, LLC, in connection with Mueschke 8; 2,700' South of Draper Road to Approximately 500' North of Draper Road, Job No. 23/0230, UPIN 161033020711, Precinct 4.
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Transmittal

Project ID (if applicable): Job No. 23/0230, UPIN 161033020711
Vendor/Entity Legal Name (if applicable): Brice Construction & Design, LLC

MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Transmittal by the Office of the County Engineer of a substantial completion certificate with Brice Construction and Design, LLC, in connection with Mueschke 8; 2,700' South of Draper Road to Approximately 500' North of Draper Road, Job No. 23/0230, UPIN 161033020711, Precinct 4.
end

Background and Discussion:
The Substantial Completion Certificate provides documentation that a capital improvement project meets the qualifications of Substantial Completion in accordance with the Contract Documents as determined by the County Engineer. Substantial Completion establishes the date on which a capital improvement enters service as a Harris County asset. The establishment and reporting of this date are important for all governmental entities as outlined in the GASB Statement #34, Capital Assets & Depreciation Guidance, August 31, 2001. These certificates provide a method by which Harris County may document and record this date.

Expected Impact:
This action establishes the date on which a capital improvement enters service as a Harris County asset.

Alternative Options:
No alternative options.


County Strategic Plan Goal: 5. Minimize the impact of climate change and disasters.
County Strategic ...