Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E, PMP, CFM, ENV SP, County Engineer
Secondary Department: Commissioner, Precinct 1
Secondary Department Head/Elected Official: Rodney Ellis, Commissioner
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): UPIN 26035FSQ7B01
Vendor/Entity Legal Name (if applicable): Infrastructure Engineering, Inc.
MWBE Contracted Goal (if applicable): 19%
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with Infrastructure Engineering, Inc. in the amount of $2,923,558.00 for Professional Engineering Services in connection with Road Improvements - Antoine Drive - Beltway 8 to Spears Road, UPIN 26035FSQ7B01, Precinct 1, MWBE Contracted Goal: 19%.
end
Background and Discussion:
Antoine Drive from Beltway 8 to Spears Road is four-lane concrete boulevard. This segment of Antoine Drive includes widening of existing pavement to accommodate bike lanes. Intersections and traffic signals to be reconstructed.
Expected Impact:
Widened concrete pavement to accommodate bike lanes along Antoine Drive project limits.
Alternative Options:
No alternative options. If not approved, the design will be delayed or cancelled.
County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): G1: Expand pedestrian and cyclist infrastructure on County-managed...
Click here for full text