Legislation Details

File #: 26-5648    Version: 1 Name:
Type: Contract - Award Status: Passed
File created: 8/14/2026 In control: Commissioners Court
On agenda: 8/25/2026 Final action: 8/25/2026
Title: Request for approval of an award on the basis of low bid to Texas Dewatering, LLC in the amount of $9,510,778 for construction of the T.C. Jester Stormwater Detention Basins - Compartment 1A and 2 for the Flood Control District, and for the County Clerk to execute any applicable bonds to be received (260210), MWBE Contracted Goal: 30%.
Attachments: 1. 26-5648 Award Job No. 260210 Texas Dewatering, LLC.pdf
Primary Department: Purchasing
Primary Department Head/Elected Official: Kimberly J. Williams, JD

Secondary Department: Flood Control District
Secondary Department Head/Elected Official: Marcus Stuckett

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

Project ID (if applicable): 260210
Vendor/Entity Legal Name (if applicable): Texas Dewatering, LLC

MWBE Contracted Goal (if applicable): 30%
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable):
Justification for 0% Grant Indirect Costs Rate (if applicable): Choose an item.

Request Summary (Agenda Caption):
title
Request for approval of an award on the basis of low bid to Texas Dewatering, LLC in the amount of $9,510,778 for construction of the T.C. Jester Stormwater Detention Basins - Compartment 1A and 2 for the Flood Control District, and for the County Clerk to execute any applicable bonds to be received (260210), MWBE Contracted Goal: 30%.
end

Background and Discussion:
Project K500-23-00-E004 includes the clearing and excavation of Detention Basins 1A and 2. Basin 1A is located south of Cypresswood Drive, east of T.C. Jester Boulevard, and north of Cypress Creek. Basin 2 is located south of Basin 1A, on the south side of Cypress Creek, adjacent to Northgate Golf Course.
The project area contains wetlands, environmentally sensitive areas, adjacent utility and pipeline easements, and bike trails. No work shall be performed within the easements except at locations where Letters of No Objection (LONOs) have been obtained for haul road crossings.
The project encompasses approximately 24 acres and includes the removal of approximately 354,926 cubic yards of excavation, as well as 4,305 square yards of Grade 2 Riprap and Granular Fill.

Expected Impact:
The proposed T.C. Jester Detention Basins will provide approximately 210 acre-feet of detention storage,...