Legislation Details

File #: 26-5227    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 7/24/2026 In control: Commissioners Court
On agenda: 8/6/2026 Final action: 8/6/2026
Title: Request for approval of a change in contract with Allgood Construction Co., Inc., in connection with final construction of West Gulf Bank Road from I45 to Airline Drive, with a deduction in the amount of $947,179.43, Job No. 22/0461-14, UPIN 19101MF0XV01, Precinct 2, MWBE Contracted Goal: 25%, MWBE Current Participation: 41.40%.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 22/0461, UPIN 19101MF0XV01
Vendor/Entity Legal Name (if applicable): Allgood Construction Co., Inc.

MWBE Contracted Goal (if applicable): 25%
MWBE Current Participation (if applicable): 41.40%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Allgood Construction Co., Inc., in connection with final construction of West Gulf Bank Road from I45 to Airline Drive, with a deduction in the amount of $947,179.43, Job No. 22/0461-14, UPIN 19101MF0XV01, Precinct 2, MWBE Contracted Goal: 25%, MWBE Current Participation: 41.40%.
end

Background and Discussion:
This project includes the construction of four 11-foot-wide concrete pavements with a 24-foot median, and an 8-foot-wide sidewalk along both sides West Gulf Bank Road from Interstate 45 Freeway to Airline Drive. It also includes drainage improvements.

- Added overrun quantities to Item 83 - 4-1/2" Concrete Sidewalk in the amount of $19,822.74, with 0 days.

- The budget variances across the project resulted from a mix of effective resource management and value engineering, and strategic procurement that led to cost savings in some areas, while necessary scope adjustments, unforeseen site conditions, and regulatory compliance requirements caused certain items to exceed their budgeted amounts. This change will deduct -$947,179.43.


Expected Impact:
Increase the total number of days for the contract.

Alternative Options:
No ac...