Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E, PMP, CFM, ENV SP, County Engineer
Secondary Department: Commissioner, Precinct 1
Secondary Department Head/Elected Official: Rodney Ellis, Commissioner
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): UPIN 261019FR8B01
Vendor/Entity Legal Name (if applicable): AIG Technical Services, LLC.
MWBE Contracted Goal (if applicable): 19%
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with AIG Technical Services LLC. in the amount of $896,057.00 for Professional Engineering Services in connection with Road Improvements - Miller Road 1 - Miller Road 3 to Sheldon - 2026, UPIN 261019FR8B01, Precinct 1, MWBE Contracted Goal: 19%.
end
Background and Discussion:
Miller Road 1 from Miller Road 3 to Sheldon Road is two-lane asphalt pavement road used by industrial/heavy truck traffic. For cost effective for maintenance, Miller Road is recommended for full reconstruction to concrete pavement. This is consistent with the recent conversion of Miller Road 2 and Miller Road 3 from asphalt to concrete pavement in the area.
Expected Impact:
Concrete pavement will last longer with less maintenance.
Alternative Options:
No alternative options. If not approved, the design will be delayed or cancelled.
County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.
Justice/Safety Initiative (Goal 1): N/...