Legislation Details

File #: 26-5158    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 7/23/2026 In control: Commissioners Court
On agenda: 8/6/2026 Final action: 8/6/2026
Title: Request for approval of a change in contract with Sprint Sand & Clay, LLC, in connection with final construction of Wortham Estates Subdivision Drainage Improvements, adding 88 calendar days, with a deduction in the amount of $109,194.32, Job No. 24/0237-2, UPIN 19103MF15701, Precinct 3, MWBE Contracted Goal: 30.79%, MWBE Current Participation: 67.10%.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 24/0237, UPIN 19103MF15701
Vendor/Entity Legal Name (if applicable): Sprint Sand & Clay, LLC

MWBE Contracted Goal (if applicable): 30.79%
MWBE Current Participation (if applicable): 67.10%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Sprint Sand & Clay, LLC, in connection with final construction of Wortham Estates Subdivision Drainage Improvements, adding 88 calendar days, with a deduction in the amount of $109,194.32, Job No. 24/0237-2, UPIN 19103MF15701, Precinct 3, MWBE Contracted Goal: 30.79%, MWBE Current Participation: 67.10%.
end

Background and Discussion:
This project is located at Huffmeister Road and Fallbrook Drive, Houston, TX 77065. The project drains into HCFCD Unit No. E133-00-00. The scope and proposed improvements include providing stormwater detention storage to reduce flooding for subdivisions which drain to E133-00-00 and E133-01-00. It will also serve to mitigate two future drainage improvement projects: (1) within the Barwood Subdivision that ultimately outfalls into E133-00-00 and (2) the future Fallbrook Drive extension to Huffmeister Road to the existing Fallbrook Drive is located at the eastern ROW of HCFCD Unit E133-00-00.

The change in contract includes the following:

The line items are adjusted to reconcile overrun and underrun quantities on the project for completion of the proposed scope of work.

* The increase of quantities on overrun...

Click here for full text