Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 24/0237, UPIN 19103MF15701
Vendor/Entity Legal Name (if applicable): Sprint Sand & Clay, LLC
MWBE Contracted Goal (if applicable): 30.79%
MWBE Current Participation (if applicable): 67.10%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Sprint Sand & Clay, LLC, in connection with final construction of Wortham Estates Subdivision Drainage Improvements, adding 88 calendar days, with a deduction in the amount of $109,194.32, Job No. 24/0237-2, UPIN 19103MF15701, Precinct 3, MWBE Contracted Goal: 30.79%, MWBE Current Participation: 67.10%.
end
Background and Discussion:
This project is located at Huffmeister Road and Fallbrook Drive, Houston, TX 77065. The project drains into HCFCD Unit No. E133-00-00. The scope and proposed improvements include providing stormwater detention storage to reduce flooding for subdivisions which drain to E133-00-00 and E133-01-00. It will also serve to mitigate two future drainage improvement projects: (1) within the Barwood Subdivision that ultimately outfalls into E133-00-00 and (2) the future Fallbrook Drive extension to Huffmeister Road to the existing Fallbrook Drive is located at the eastern ROW of HCFCD Unit E133-00-00.
The change in contract includes the following:
The line items are adjusted to reconcile overrun and underrun quantities on the project for completion of the proposed scope of work.
* The increase of quantities on overrun...
Click here for full text