Legislation Details

File #: 26-5157    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 7/23/2026 In control: Commissioners Court
On agenda: 8/6/2026 Final action: 8/6/2026
Title: Request for approval of an amendment to an agreement with GC Engineering, Inc. in the amount of $77,717.00 for Professional Engineering Services to provide improvements to Telge Rd Segment 5 - from 1,780-ft North of Telge Ranch Rd to 300-ft North of Grant Rd - 2014, UPIN 23103MF2QF01, Precinct 3, MWBE Contracted Goal: 71%, MWBE Current Participation: 82.18%.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: Commissioner, Precinct 3
Secondary Department Head/Elected Official: Tom S. Ramsey, P.E., Commissioner

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): 23103MF2QF01
Vendor/Entity Legal Name (if applicable): GC Engineering, Inc.

MWBE Contracted Goal (if applicable): 71%
MWBE Current Participation (if applicable): 82.18%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of an amendment to an agreement with GC Engineering, Inc. in the amount of $77,717.00 for Professional Engineering Services to provide improvements to Telge Rd Segment 5 - from 1,780-ft North of Telge Ranch Rd to 300-ft North of Grant Rd - 2014, UPIN 23103MF2QF01, Precinct 3, MWBE Contracted Goal: 71%, MWBE Current Participation: 82.18%.
end

Background and Discussion:
Project involves the expansion of a two lane roadway to a 4-lane concrete boulevard with curb and gutter, and storm drain. Consultant to provide additional services related to detention basin geotechnical testing as well as the design of turn lane modifications.

Expected Impact:
This amendment will allow the project to be optimized to better fit the conditions.

Alternative Options:
An alternative would be not to conduct the study and design which will result in less than an optimal solution.

County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: F: Ensure safety and security for all using the county's transportation network in alignment with the County's Vision Zero ...

Click here for full text