Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: Commissioner, Precinct 4
Secondary Department Head/Elected Official: Lesley Briones, Commissioner
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): UPIN 24104MF38Q01
Vendor/Entity Legal Name (if applicable): Entech Civil Engineers, Inc.
MWBE Contracted Goal (if applicable): 19.6%
MWBE Current Participation (if applicable): 20.21%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of an amendment to an agreement with Entech Civil Engineers, Inc. for Professional Engineering Services to conduct a feasibility study in connection with Sidewalk - Energy Corridor and Multimodal Connectivity -- 2023, UPIN 24104MF38Q01, Precinct 4, MWBE Contracted Goal: 19.6%, MWBE Current Participation: 20.21%.
end
Background and Discussion:
This goal of this project is to conduct and complete a feasibility study for the design and construction phases of sidewalk and safety improvements along Park Row drive, North Dairy Ashford and Dairy Ashford Road. The project includes completing a feasibility study for designing and construction of a 6-foot-wide Sidewalk along the North and South, ADA compliant traffic elements and spot improvements along the entire length of the roadway in the project limit. This amendment will provide additional Professional services to support extending improvement and safety from Addicks Trail to Terry Hershey Trail along the Park Row Blvd.
Expected Impact:
This project focuses on enhancing the mobility and connectivity options of non-motorized modes between the various land uses and developments in the Ener...
Click here for full text