Primary Department: Flood Control District
Primary Department Head/Elected Official: Marcus Y. Stuckett, P.E., CFM
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): N/A
Vendor/Entity Legal Name (if applicable): N/A
MWBE Contracted Goal (if applicable): 11.23%
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of an agreement with Amani Engineering, Inc., in the amount of $1,245,428, to provide design, bidding, and construction phase services in support of the Bellfort Area Stormwater Conveyance Improvements project (Sims Bayou Watershed, Bond ID F-92, Project ID C116-00-00-C001, Agreement No. 2026-26, Precinct 2, MWBE Contracted Goal: 11.23%).
end
Background and Discussion:
This agreement will provide design, bidding and construction phase engineering services for Belfort Area Conveyance Improvements. This project occurs in the 1st quartile under the 2022 Prioritization Framework approved by Commissioners Court.
Expected Impact:
The project seeks to reduce flood risks and strengthen resiliency in the Sims Bayou watershed by reducing the risk of flooding for 26 structures, 1.08 miles of roadway, and 29 acres of area.
Alternative Options:
The alternative to approving this item would be finding another consultant, which would result in delayed implantation of the project.
County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.
Justice...
Click here for full text