Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E, PMP, CFM, ENV SP, County Engineer
Secondary Department: Commissioner, Precinct 1
Secondary Department Head/Elected Official: Rodney Ellis, Commissioner
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): UPIN 26101M37NB01
Vendor/Entity Legal Name (if applicable): Infrastructure Engineering, Inc.
MWBE Contracted Goal (if applicable): 19%
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with Infrastructure Engineering, Inc. in the amount of $1,632,783.00 for Professional Engineering Services in connection with TC Jester Boulevard improvement from Aldine Western Road to Beltway 8, UPIN 26101M37NB01, Precinct 1, MWBE Contracted Goal: 19%.
end
Background and Discussion:
TC Jester Boulevard is a major throughfare. The missing 1,000-foot segment of TC Jester Boulevard between Aldine Westfield Road and Beltway 8 will be designed and constructed to complete the corridor including a bridge over Greens Bayou, reduce congestion on Veterans Memorial Drive, improve access to the Houston National Cemetery, and create a connection point for future Greens Bayou trail.
Expected Impact:
Reduce traffic congestion and improve access to the Houston National Cemetery. Complete the missing segment of the Major Throughfare.
Alternative Options:
No alternative options. If not approved, study and design will be delayed or cancelled.
County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: H: Improve the condit...