File #: 26-4748    Version: 1 Name:
Type: Contract - Award Status: Passed
File created: 7/15/2026 In control: Commissioners Court
On agenda: 7/30/2026 Final action: 7/30/2026
Title: Request for approval of an award on the basis of low bid to Juan & Son Contracting LLC in the amount of $335,791 for subdivision drainage improvements - Lakeshore for Precinct 3, and for the County Clerk to execute any applicable bonds to be received (260154), MWBE Contracted Goal: 24.43%.
Primary Department: Purchasing
Primary Department Head/Elected Official: Kimberly J. Williams, JD

Secondary Department: Commissioner, Precinct 3
Secondary Department Head/Elected Official: Tom Ramsey

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

Project ID (if applicable): 260154
Vendor/Entity Legal Name (if applicable): Juan & Son Contracting LLC

MWBE Contracted Goal (if applicable): 24.43%
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of an award on the basis of low bid to Juan & Son Contracting LLC in the amount of $335,791 for subdivision drainage improvements - Lakeshore for Precinct 3, and for the County Clerk to execute any applicable bonds to be received (260154), MWBE Contracted Goal: 24.43%.
end

Background and Discussion:
Based on the bid results and the recommendation of the Office of the County Engineer (OCE) and the design consultant, Michael Baker International, Inc., it is recommended that the lowest responsive and responsible bidder, Juan & Son Contracting, LLC, be awarded the contract for the Construction of Subdivision Drainage Improvements - Lakeshore - 2024 for Harris County Precinct 3.

Expected Impact:
Awarding the contract will allow the recommended bidder to proceed with the construction of the Subdivision Drainage Improvements - Lakeshore - 2024 project. The project consists of installing a secondary storm sewer system and a new outfall to Lake Houston to improve drainage and reduce flood risk for the properties located at 13718, 13722, and 13726 Elm Shores Drive.

Alternative Options:
The alternative is not to award the contract. If no action is taken, the upgrades will not be constructed.