Primary Department: Flood Control District
Primary Department Head/Elected Official: Marcus Y. Stuckett, P.E., CFM
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): P500-06-00-E007
Vendor/Entity Legal Name (if applicable): Arrowstone Contracting LLC
MWBE Contracted Goal (if applicable): 31.50%
MWBE Current Participation (if applicable): 0
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of change in contract No. 1 with Arrowstone Contracting, LLC, for the Lauder Stormwater Detention Basin - Compartment 2 (Greens Bayou Watershed, Project ID P500-06-00-E007, Job No. 25/0394, Precinct 2, MWBE Contracted Goal: 31.50%).
end
Background and Discussion:
This project is for the construction of the second compartment of a sequence of detention basins to help reduce the risk of flood damage in the P138-00-00 channel that drains to Greens Bayou. The purpose of this contract change is to increase the quantity of the pay item for alligators snapping turtle exclusion fence. The contract change includes $0/0 days.
Expected Impact:
This change will allow the contractor to construct the project so that Harris County can realize intended flood risk reduction benefits.
Alternative Options:
This is an active construction contract, so there are not many alternatives to approving a change order other than cancelling the contract which is not recommended as doing so would substantially delay the remaining work in the construction contract.
County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: H: Impro...