Primary Department: Purchasing
Primary Department Head/Elected Official: Kimberly J. Williams, JD
Secondary Department: Flood Control District
Secondary Department Head/Elected Official: Marcus Stuckett
Regular or Supplemental RCA: Regular RCA
Type of Request: Transmittal
Project ID (if applicable): 260100
Vendor/Entity Legal Name (if applicable): Takco, Inc.
MWBE Contracted Goal (if applicable): 15.47%
MWBE Current Participation (if applicable):
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable):
Justification for 0% Grant Indirect Costs Rate (if applicable): Choose an item.
Request Summary (Agenda Caption):
title
Transmittal by the Office of the Purchasing Agent of an award of a Community Development Block Grant Disaster Recovery (CDBG-DR)/Community Development Block Grant Mitigation (CDBG-MIT) Program(s) project on the basis of low bid(s) to Takco, Inc. in the amount of $42,614,329 for construction of the Genoa Red Bluff Stormwater Detention Basins - Phase 2 - for the Flood Control District, and for the County Clerk to execute any applicable bonds to be received (260100), MWBE Contracted Goal: 15.47%.
end
Background and Discussion:
The proposed Genoa Red Bluff Stormwater Detention (SWD) basins are located within the Armand Bayou (HCFCD Unit B100-00-00) watershed along Spring Gully (HCFCD Unit B109-00-00). The site is partially located within the City of Pasadena. The proposed SWD basins are intended to mitigate the future channel improvements from La Porte's Brookglen Regional Plan, which is a flood risk reduction plan to relieve the repetitive flooding in the Brookglen neighborhood located in La Porte to the north. Phase 1 construction has been completed under B509-03-00-E001. Phase 2 design and construction includes expansion of the detention basin to its full capacity. Project is being funded by the CDBG-DR program.
Expected Impact:
This project seeks to reduce flo...
Click here for full text