Primary Department: Toll Road Authority
Primary Department Head/Elected Official: Roberto Trevi?o, P.E., Executive Director
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Renewal
Project ID (if applicable): 24/0012
Vendor/Entity Legal Name (if applicable): Premier Demolition Services, LLC
MWBE Contracted Goal (if applicable): 20%
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a renewal option with Epoxy Design Systems, Inc for concrete repairs at the Washburn Tunnel and other related items for the period of August 1, 2026 to July 31, 2027, at a cost of $890,708.62, and for the County Clerk to execute any applicable bonds to be received (240012) (Precinct 2, MWBE Contract Goal: 20%).
end
Background and Discussion:
This authorization is for the second of four renewal options with Epoxy Design Systems, Inc for concrete repairs at the Washburn Tunnel and other related items for the period of August 1, 2026, to July 31, 2027.
The approval of this renewal allows HCTRA to continue concrete crack and spalling repairs of the tunnel liner, masonry brick, and other related items at the Washburn Tunnel to ensure continued proactive maintenance of HCTRA's infrastructure.
Expected Impact:
Funding will come from Harris County Toll Road Authority.
Alternative Options:
No other recommended solutions for this identified need.
County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: N/A
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): N/A
...
Click here for full text