Legislation Details

File #: 26-4403    Version: 1 Name:
Type: Contract - Award Status: Passed
File created: 6/25/2026 In control: Commissioners Court
On agenda: 7/9/2026 Final action: 7/9/2026
Title: Request for approval to execute an agreement with PGAL, Inc in the amount of $1,166,365.00, for professional architectural and engineering services in connection with Facility Improvements - Deussen Park - 2026, UPIN 26101IC4YY01, Precinct 1, MWBE Contracted Goal: 19%.
Sponsors: Mony Hossain
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP, County Engineer

Secondary Department: Commissioner, Precinct 1
Secondary Department Head/Elected Official: Rodney Ellis, Commissioner

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

Project ID (if applicable): 26101IC4YY01
Vendor/Entity Legal Name (if applicable): PGAL, Inc

MWBE Contracted Goal (if applicable): 19%
MWBE Current Participation (if applicable):
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with PGAL, Inc in the amount of $1,166,365.00, for professional architectural and engineering services in connection with Facility Improvements - Deussen Park - 2026, UPIN 26101IC4YY01, Precinct 1, MWBE Contracted Goal: 19%.
end

Background and Discussion:
Precinct 1 wishes to make improvements to Deussen Park including improvements to the existing Senior Center and Nature Center, and a new amphitheater. This Award is for Architectural/Engineering firm to provide design services.

Expected Impact:
Approval to award contract to the selected vendor of Architectural/Engineering design services will allow the project to be designed to provide benefits to the community surrounding Deussen Park.

Alternative Options:
Attempting to maintain the facility as-will result in significant repair and maintenance costs of the degrading existing facilities.

County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: N/A
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): H4: Consistently embed sustainability considerations in the pro...

Click here for full text