File #: 26-4401    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 6/25/2026 In control: Commissioners Court
On agenda: 7/9/2026 Final action: 7/9/2026
Title: Request for approval of change in contract No. 1 with Environmental Allies, Inc., for the Brookglen Stormwater Detention Basin - Phase 2 (Armand Bayou Watershed, Bond ID C-06, Project ID B512-02-00-E002, Job No. 25/0353, Precinct 2, MWBE Contracted Goal: 27.26%, MWBE Current Participation: 23.71%).
Primary Department: Flood Control District
Primary Department Head/Elected Official: Marcus Y. Stuckett, P.E., CFM, Executive Director

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): B512-02-00-E002
Vendor/Entity Legal Name (if applicable): Environmental Allies, Inc.

MWBE Contracted Goal (if applicable): 27.26%
MWBE Current Participation (if applicable): 23.71%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of change in contract No. 1 with Environmental Allies, Inc., for the Brookglen Stormwater Detention Basin - Phase 2 (Armand Bayou Watershed, Bond ID C-06, Project ID B512-02-00-E002, Job No. 25/0353, Precinct 2, MWBE Contracted Goal: 27.26%, MWBE Current Participation: 23.71%).
end

Background and Discussion:
This change in contract is needed to complete the construction contract for this project. Contract Change No. 1 includes help to reduce the risk of flood damage in the Armand Bayou Watershed by constructing the Brookglen Stormwater Detention Basin project in the Brookglen Subdivision. The Project is the second compartment of a suggested sequencing plan of proposed projects. The purpose of this contract change is to increase the quantity of the pay item for stabilized construction access, correct the unit of measurement for sidewalk items, and remove the Harris County Engineering Department General Conditions. The contract change includes $0 and 0 days.

Expected Impact:
This change will allow the contractor to construct the project so that Harris County can realize intended flood
risk reduction benefits.

Alternative Options:
This is an active construction contract, so there are no...