Legislation Details

File #: 26-4397    Version: 1 Name:
Type: Contract - Award Status: Passed
File created: 6/25/2026 In control: Commissioners Court
On agenda: 7/9/2026 Final action: 7/9/2026
Title: Request for approval to execute an agreement with Autoarch Architects, LLC in the amount of $395,000.00, for professional architectural and engineering services in connection with Facility Improvements - Lincoln Park - 2026, UPIN 26101NN3NN01, Precinct 1, MWBE Contracted Goal: 19.00%.
Sponsors: Mony Hossain
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP, County Engineer

Secondary Department: Commissioner, Precinct 1
Secondary Department Head/Elected Official: Rodney Ellis, Commissioner

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

Project ID (if applicable): 26101NN3NN01
Vendor/Entity Legal Name (if applicable): Autoarch Architects, LLC

MWBE Contracted Goal (if applicable): 19.00%
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with Autoarch Architects, LLC in the amount of $395,000.00, for professional architectural and engineering services in connection with Facility Improvements - Lincoln Park - 2026, UPIN 26101NN3NN01, Precinct 1, MWBE Contracted Goal: 19.00%.
end

Background and Discussion:
Precinct 1 wishes to make improvements to Lincoln Park including a new structure, connection to the Community Center via a breezeway or enclosure, additional parking stalls, and renovations to the restrooms in the Community Center. This Award is for Architectural/Engineering firm to provide design services through the design phase, bidding phase and construction phase of the project.

Expected Impact:
Approval of awarding a contract to the selected vendor of A/E design services will allow the project to be designed to provide benefits to the community surrounding Lincoln Park.

Alternative Options:
Attempt to maintain the facility as is however, this will result in significant repair and maintenance costs of the degrading facilities.

County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastruc...

Click here for full text