Legislation Details

File #: 26-4188    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 6/23/2026 In control: Commissioners Court
On agenda: 7/9/2026 Final action: 7/9/2026
Title: Request for approval of a change in contract with Blazey Construction Services, LLC, in connection with final construction of Tower Oaks Plaza Subdivision Drainage Improvements - 2018, with a deduction in the amount of $859,217.24, Job No. 23/0027-7, UPIN 19103MF14801, Precinct 3, MWBE Contracted Goal: 31%, MWBE Current Participation: 100%.
Sponsors: Mony Hossain
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 23/0027, UPIN 19103MF14801
Vendor/Entity Legal Name (if applicable): Blazey Construction Services, LLC

MWBE Contracted Goal (if applicable): 31%
MWBE Current Participation (if applicable): 100%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Blazey Construction Services, LLC, in connection with final construction of Tower Oaks Plaza Subdivision Drainage Improvements - 2018, with a deduction in the amount of $859,217.24, Job No. 23/0027-7, UPIN 19103MF14801, Precinct 3, MWBE Contracted Goal: 31%, MWBE Current Participation: 100%.
end

Background and Discussion:
The project is in northwest Harris County, north of Cypress North Houston Road and east of North Eldridge Parkway. The existing drainage system consists of roadside ditches which outfall to the west of the subdivision via 24 to 36-inch pipes at three points along HCFCD Channel K161-00-00 and to Cypress Creek from a fourth outfall at the northeast corner of the subdivision. The scope and proposed improvements include bringing the subdivision roadways into compliance with Harris County Standards, constructing storm sewer underlying roadside ditches, regarding roadside ditches, upsizing and replacing driveway culverts, replacing driveways, and the construction of a storm water detention basin.

The change in contract includes the following:

The line items are adjusted to reconcile overrun and underrun quantities on the...

Click here for full text