Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: Commissioner, Precinct 3
Secondary Department Head/Elected Official: Tom S. Ramsey, P.E., Commissioner
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): UPIN 19104MF14S01
Vendor/Entity Legal Name (if applicable): KCI Technologies, Inc.
MWBE Contracted Goal (if applicable): 6%
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval to execute a Construction Phase Professional Engineering Services agreement with KCI Technologies, Inc. in the amount of $148,306.00 in connection with the Norchester Subdivision Drainage Improvements - 2018 project, UPIN 19104MF14S01, Precinct 3, MWBE Contracted Goal: 6%.
end
Background and Discussion:
This project is in northwest Harris County in the Cypress Creek watershed. Norchester Subdivision consists of an existing underground storm sewer system that drains into the existing Anderson Ditch and K10000-00 channel. The scope of the project consisted of upsizing existing storm sewer pipes in the neighborhood, adding additional storm sewer pipes, and increasing the number of inlets to the system to reduce localized flooding in the neighborhood. A new detention basin will also be required for mitigation.
Expected Impact:
This project seeks to reduce flooding and strengthen resiliency in Harris County by assisting in the alleviation of structural floods in the Norchester subdivision. No impact to project cost, schedule or staffing anticipated.
Alternative Options:
The County could elect to approve or choose to reject it. However, if not app...
Click here for full text