Legislation Details

File #: 26-4155    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 6/23/2026 In control: Commissioners Court
On agenda: 7/9/2026 Final action: 7/9/2026
Title: Request for approval of a change in contract with MC2 Civil, LLC in connection with final construction of Intersection Improvement - Stuebner Airline Road at Kleppel Road - 2023, adding 45 calendar days, with an addition in the amount of $139,177.64, Job No. 23/0190-1, UPIN 24103MF33W01, Precinct 3, MWBE Contracted Goal: 28%, MWBE Current Participation: 29.67%.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 23/0190, UPIN 24103MF33W01
Vendor/Entity Legal Name (if applicable): MC2 Civil, LLC

MWBE Contracted Goal (if applicable): 28%
MWBE Current Participation (if applicable): 29.67%
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with MC2 Civil, LLC in connection with final construction of Intersection Improvement - Stuebner Airline Road at Kleppel Road - 2023, adding 45 calendar days, with an addition in the amount of $139,177.64, Job No. 23/0190-1, UPIN 24103MF33W01, Precinct 3, MWBE Contracted Goal: 28%, MWBE Current Participation: 29.67%.
end

Background and Discussion:
Bridge Repair - Stuebner Airline Road Bridge K100 is located at Stuebner Airline Road, crossing over Cypress Creek. The Scope of Work for this project includes, but not limited to concrete spall repairs, bearing pads replacements, erosion control and slope regrading, guardrail repairs, concrete channel lining, removal of structural - abutment backwall at the Stuebner Airline Road bridge over HFCD Channel K100-00-00 (Cypress Creek) within Harris County, Precinct 3.

The Final Adjustment and Changes in the contract include:

o PCO# 2 - Adding a new line item #110 for the Standard Manhole to the complete the work proposed in the design plan with an additional cost of $7,361.07 and zero calendar days.

o PCO# 4 - Requesting to correct the Unit of Measurement for the existing line item #5 - "Borrow" from Square Yard to C...

Click here for full text