Legislation Details

File #: 26-4154    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 6/23/2026 In control: Commissioners Court
On agenda: 7/9/2026 Final action: 7/9/2026
Title: Request for approval of a change in contract with DVL Enterprises LLC in connection with Mound Road Extension from Greenhouse Road along Spring Drive to Cypress Drive - Segment 2, adding 30 calendar days, with an addition in the amount of $8,360.00, Job No. 24/0265-3, UPIN 24103MF3C501, Precinct 3, MWBE Contracted Goal: 27.62%, MWBE Current Participation: 19.65%.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 24/0265, UPIN 24103MF3C501
Vendor/Entity Legal Name (if applicable): DVL Enterprises, LLC

MWBE Contracted Goal (if applicable): 27.62%
MWBE Current Participation (if applicable): 19.65%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with DVL Enterprises LLC in connection with Mound Road Extension from Greenhouse Road along Spring Drive to Cypress Drive - Segment 2, adding 30 calendar days, with an addition in the amount of $8,360.00, Job No. 24/0265-3, UPIN 24103MF3C501, Precinct 3, MWBE Contracted Goal: 27.62%, MWBE Current Participation: 19.65%.
end

Background and Discussion:
The project section of Mound Road is a 4-lane, median-divided concrete roadway extended from Greenhouse Road and transitioning to 2-lane asphalt and gravel roadways terminating at Cypress Drive Mound Road extension project to be divided into two segments to provide accessibility to adjacent developments and finalize the outfall design servicing the project. This change order compensates the contractor for additional work and time resulting from design revisions, required field clarifications, and necessary construction adjustments, all of which were essential to completing the project.

The change in contract includes the following:
? Prime Coat 880 GAL $6,160.00
? Tack Coat 440 GAL $2,200.00



Expected Impact:
This change will allow the Contractor to be properly compensated for the...

Click here for full text