Legislation Details

File #: 26-4150    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 6/23/2026 In control: Commissioners Court
On agenda: 7/9/2026 Final action: 7/9/2026
Title: Request for approval of a change in contract with Spawglass Construction Corp. in connection with Challenger 7 Improvements, adding 215 calendar days, with an addition in the amount of $65,865.78, Job No. 24/0264-4, UPIN 20101MF1F101, Precinct 2, MWBE Contracted Goal: 41%, MWBE Current Participation: 42.85%.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 24/0264, UPIN 20101MF1F101
Vendor/Entity Legal Name (if applicable): Spawglass Construction Corp.

MWBE Contracted Goal (if applicable): 41%
MWBE Current Participation (if applicable): 42.85%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Spawglass Construction Corp. in connection with Challenger 7 Improvements, adding 215 calendar days, with an addition in the amount of $65,865.78, Job No. 24/0264-4, UPIN 20101MF1F101, Precinct 2, MWBE Contracted Goal: 41%, MWBE Current Participation: 42.85%.
end

Background and Discussion:
Challenger 7 Park - Boardwalk Renovation project includes work in three distinct areas. The existing boardwalk area will include removal of the existing boardwalk and replacement with a new structure. Learning components including an immersive classroom, outdoor classroom, and areas for future signage will be identified. The project also contains the addition of a trailhead with bike parking. The area near the boat ramp will be repurposed to include additional walking trails, seating area, floating kayak launch, and planting.

The Changes in contract include:
* Adding a new line item is needed to adjust the 6-inch drainpipe at Rocketship entrance to address the flow of water with additional cost of $3,951.19 and zero calendar days.
* Adding a new line item to install 22 Inches I-Beam at overlook Pavillion to support the WC with additional costs of ...

Click here for full text