Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 24/0373, UPIN 23102MF2UN01
Vendor/Entity Legal Name (if applicable): Environmental Allies, Inc.
MWBE Contracted Goal (if applicable): 32.17%
MWBE Current Participation (if applicable): 19.13%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Environmental Allies, Inc., in connection with Roadway - Blackhawk Blvd - Scarsdale Blvd to Sam Houston Pkwy - P2 - 2022, with an addition in the amount of $21,676.52, Job No. 24/0373-5, UPIN 23102MF2UN01, Precinct 2, MWBE Contracted Goal: 32.17%, MWBE Current Participation: 19.13%.
end
Background and Discussion:
Harris County intends to provide improvements to Blackhawk Boulevard from Scarsdale Boulevard to South Sam Houston Parkway East, within Precinct 2 including sidewalks, replacing damaged roadway pavement, new curb ramps, etc.
This Change Order is tied with Multiple PCOs (PCO-9 through PCO-12) address quantity overruns required to bring field conditions into compliance with ADA standards and project directives:
PCO- 9 and PCO-12: Two driveways (STA 137+68 EB and STA 134+60 WB) the original construction plans did not include the removal and reconstruction of the driveway instead, they specified tying the existing driveway into the proposed sidewalk. However, the existing driveway does not meet ADA requirements, as its slope exceeds the allowable limit for a sidewalk crossing. Both locations require removal and reconstruction u...