Legislation Details

File #: 26-3945    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 6/5/2026 In control: Commissioners Court
On agenda: 6/25/2026 Final action: 6/25/2026
Title: Request for approval of a change in contract with D & W Contractors, Inc., in connection with Highland Ridge and Highland Estates Subdivision Drainage Improvements - 2018, with no change in the amount, Job No. 25/0357-2, UPIN 19102MF13001, Precinct 3, MWBE Contracted Goal: 16.13%, MWBE Current Participation: 37.34%.
Sponsors: Mony Hossain
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 25/0357, UPIN 19102MF13001
Vendor/Entity Legal Name (if applicable): D & W Contractors, Inc.

MWBE Contracted Goal (if applicable): 16.13%
MWBE Current Participation (if applicable): 37.34%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with D & W Contractors, Inc., in connection with Highland Ridge and Highland Estates Subdivision Drainage Improvements - 2018, with no change in the amount, Job No. 25/0357-2, UPIN 19102MF13001, Precinct 3, MWBE Contracted Goal: 16.13%, MWBE Current Participation: 37.34%.
end

Background and Discussion:
The project is located in northeast Harris County in the Spring Gully & Goose Creek and San Jacinto River watersheds. It is north of Barbers Hill Road and east of Sralla Road. The existing drainage consists of roadside ditches and outfalls to HCFCD channel O119-00-00. The proposed improvements are to regrade roadside ditches, upsize culverts, upsize outfalls and construct new outfalls, and construct a detention pond within the O119-00-00 channel for mitigation.

The change in contract includes the following:

The line items are adjusted to reconcile overrun and underrun quantities to the project for completion of the proposed scope of work.

* The increase of quantities for line 18 and 30 for an addition in the amount of $17,700.00 and zero (0) days.

* The decrease in quantities for line item 38 for a deduction in the amount of $17,700.00 and...

Click here for full text