Legislation Details

File #: 26-3929    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 6/4/2026 In control: Commissioners Court
On agenda: 6/25/2026 Final action: 6/25/2026
Title: Request for approval of a change in contract with Precise Services Inc., in connection with Cedar Bayou Park East and West Subdivision Drainage Improvements - 2018, adding 95 calendar days, with an addition in the amount of $507,150.00, Job No. 24/0408-2, Bond Fund, UPIN 19102MF15W01, Precinct 2, MWBE Contracted Goal: 22.81%, MWBE Current Participation: 100%.
Sponsors: Mony Hossain
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 24/0408, UPIN 19102MF15W01
Vendor/Entity Legal Name (if applicable): Precise Services Inc.

MWBE Contracted Goal (if applicable): 22.81%
MWBE Current Participation (if applicable): 100%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Precise Services Inc., in connection with Cedar Bayou Park East and West Subdivision Drainage Improvements - 2018, adding 95 calendar days, with an addition in the amount of $507,150.00, Job No. 24/0408-2, Bond Fund, UPIN 19102MF15W01, Precinct 2, MWBE Contracted Goal: 22.81%, MWBE Current Participation: 100%.
end

Background and Discussion:
This project entails the construction of storm sewer drainage to convey drainage in the Cedar Bayou Park East
and West Subdivision from Sjolander Road to Bayou Boulevard.

The change in contract includes the following:

The line items have been adjusted to reconcile overrun quantities for completion of the proposed scope of work.

* The increase in quantities for line item 26 - Temporary Shoring in the amount of $498,550.00 zero (o) days.
* The increase in quantities for line items 42 - TYPE A INLET UP TO 30-inches and item 47 - 24-INCH RCP in the amount of $8,600 and five (5) days.
* Added 90 days to the contract due to delay caused by CenterPoint Energy utility conflict with the proposed 6'x3' RCB installation, with no additional cost.

The above additions result in a net change in the amount of $507,15...