Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: Commissioner, Precinct 4
Secondary Department Head/Elected Official: Lesley Briones
Regular or Supplemental RCA: Regular RCA
Type of Request: Report
Project ID (if applicable): UPIN: 24104MF3A401
Vendor/Entity Legal Name (if applicable): Bowman Engineering & Consulting Inc.
MWBE Contracted Goal (if applicable): 19.60%
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a Study Report prepared by Bowman Engineering & Consulting, Inc, for Peek Road - from Stockdick School Road to Beckendorff Road - 2023, UPIN 24104MF3A401, Precinct 4.
end
Background and Discussion:
Peek Road is an existing 2-lane asphalt road with roadside ditches and bridge crossing over South Mayde Creek. The project proposes improving the existing conditions to a 4-lane concrete boulevard with medians, underground storm sewer, sidewalks and expanded bridge crossing.
Expected Impact:
The project seeks to improve transportation and pedestrian mobility by improving the road conditions to enhance traffic flow and provide pedestrian friendly infrastructure by constructing sidewalks.
Alternative Options:
If the County could not elect to approve this request, the consultant would not be able to complete the scope of work.
County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: G: Expand and optimize multimodal transportation options.
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): G2: Implement designa...