Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: Commissioner, Precinct 2
Secondary Department Head/Elected Official: Adrian Garcia, Commissioner
Regular or Supplemental RCA: Regular RCA
Type of Request: Interlocal Agreement
Project ID (if applicable): UPIN 261026T1WB01
Vendor/Entity Legal Name (if applicable): City of La Porte
MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: Exempt - Interlocal/Cooperative Agreement
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval to execute a joint participation interlocal agreement with the City of La Porte to study and design drainage improvements along 6th Street from W. Madison Street to W. Main Street and all related appurtenances, UPIN 261026T1WB01, Precinct 2.
end
Background and Discussion:
According to the Climate and Economic Justice Screening Tool, the project area is designated as a disadvantaged community under the criteria established by the Justice40 Initiative. The existing drainage infrastructure, which is more than 70 years old, no longer meets current engineering and capacity standards. Additionally, based on FEMA Repetitive Loss and Severe Repetitive Loss data, the area has sustained frequent and significant flood-related damages resulting from extreme rainfall events.
Expected Impact:
The project will result in reduced flood risks for current and future development in the area and could provide economic development by making the area less susceptible to extreme rainfall events.
Alternative Options:
The alternative option for this proposal would be denial of this project which may have a negative impact on surrounding communities.
County Strategic Plan Go...