Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 21/0350, UPIN 19101MF0YA01
Vendor/Entity Legal Name (if applicable): WadeCon, LLC
MWBE Contracted Goal (if applicable): 16%
MWBE Current Participation (if applicable): 10.95%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
...title
Request for approval of a change in contract with WadeCon, LLC, in connection with final construction of Airline Drive from West Gulf Bank Road to West Road, adding 177 calendar days, with a deduction in the amount of $658,077.77, Job No. 21/0350-6, UPIN 19101MF0YA01, Precinct 2, MWBE Contracted Goal: 16%, MWBE Current Participation: 10.95%.
...end
Background and Discussion:
Project includes the construction of sidewalks, driveways, medians, landscaping, irrigation system and street lighting to improve pedestrian access and management of vehicular access.
This Change Order addresses time extensions only, with a total cost of $46,292.78. This cost will be covered entirely by reallocating funds from Bid Item 215, and no additional funds will be added to the contract. New bid items will be established to account for the work, and calendar days will be added to the contract schedule as outlined below:
PCO# 20 - Signposts and Breakaway Base
The project plans originally specified the installation of roadway signs using square posts with non-breakaway bases for signs placed on natural ground and rigid surfaces. However, the owner has requested a change to use round, yellow-coated posts for all signs within t...
Click here for full text