Title: Request for approval of an award on the basis of low bid to DVL Enterprises, LLC in the amount of $2,529,680 for minor repairs for White Oak Bayou (2026) for the Flood Control District, and for the County Clerk to execute any applicable bonds to be received (260098), MWBE Contracted Goal: 14.92%.
Primary Department: Purchasing
Primary Department Head/Elected Official: Kimberly J. Williams, JD

Secondary Department: Flood Control District
Secondary Department Head/Elected Official: Tina Petersen

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

Project ID (if applicable):260098
Vendor/Entity Legal Name (if applicable): DVL Enterprises, LLC

MWBE Contracted Goal (if applicable): 14.92%
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of an award on the basis of low bid to DVL Enterprises, LLC in the amount of $2,529,680 for minor repairs for White Oak Bayou (2026) for the Flood Control District, and for the County Clerk to execute any applicable bonds to be received (260098), MWBE Contracted Goal: 14.92%.
end

Background and Discussion:
The 2026 White Oak Bayou Minor Repairs includes only concrete sideslope or bottom shelf channel lining repair sites. There are 168 repair sites. The project limits are from upstream of Yale to Cole Creek (E117-00-00). These repairs address deficiencies within the Federal Section of White Oak Bayou. Repair sites were not included downstream of Yale because the channel is not accessible due to the TXDOT project for the IH-45 to I-10 connector. HCFCD received four (4) responsive bids on April 27, 2026 for this project. The recommendation is to award the project to the lowest responsible bidder, DVL Enterprises, LLC.

Expected Impact:
Improving the concrete channel lining of White Oak Bayou will safeguard the conveyance capacity of the
channel for the watershed.

Alternative Options:
The "Do nothing" option or choosing not to improve the Federal Reach of White Oak Bayou risks
increased flooding to the watershed. Cho...