Title: Request for approval of an award on the basis of low bid to DVL Enterprises, LLC in the amount of $1,809,182 for channel improvements for Pillot Gully for the Flood Control District, and for the County Clerk to execute any applicable bonds to be received (260110), MWBE Contracted Goal: 16.11%.
Primary Department: Purchasing
Primary Department Head/Elected Official: Kimberly J. Williams, JD

Secondary Department: Flood Control District
Secondary Department Head/Elected Official: Tina Petersen

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

Project ID (if applicable): 260110
Vendor/Entity Legal Name (if applicable): DVL Enterprises, LLC

MWBE Contracted Goal (if applicable): 16.11%
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of an award on the basis of low bid to DVL Enterprises, LLC in the amount of $1,809,182 for channel improvements for Pillot Gully for the Flood Control District, and for the County Clerk to execute any applicable bonds to be received (260110), MWBE Contracted Goal: 16.11%.
end

Background and Discussion:
Channel K140-00-00 is a tributary of Cypress Creek in Harris County Precinct 3. The channel was originally designed as an earthen trapezoidal section from Louetta Rd to Vintage Preserve Pkwy in the 1950's and was deepened and widened in the 1980s. The channel bottom has been significantly damaged by erosion and needs to be stabilized to prevent further damage. The project scope includes repairing side slope and flowline failures, storm sewer outfalls, backslope drainage systems, erosion armoring using Riprap and excess sediment removal. Repairs include the placement of select fill material, placement of well graded mix and the placement of grade #1 riprap. Channel cross sections will be reconstructed with a maximum 3:1 (H:V) slope throughout.

Expected Impact:
The intent of this contract is to return the channel to the original configuration and capacity to assure it performs as intended. This will benefit the surr...