Primary Department: Purchasing
Primary Department Head/Elected Official: Kimberly J. Williams, JD
Secondary Department: Commissioner, Precinct 4
Secondary Department Head/Elected Official: Lesley Briones
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): 260085
Vendor/Entity Legal Name (if applicable): iCON GC, LLC
MWBE Contracted Goal (if applicable): 29.80%
MWBE Current Participation (if applicable):
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable):
Justification for 0% Grant Indirect Costs Rate (if applicable): Choose an item.
Request Summary (Agenda Caption):
title
Request for approval of an award on the basis of low bid to iCON GC, LLC in the amount of $4,276,639 for roadway reconstruction of Porter Road segment 3 from 270' N of Morton Ranch Road to 545' S of Clay Road for Precinct 4, and for the County Clerk to execute any applicable bonds to be received (260085), MWBE Contracted Goal: 29.80%.
end
Background and Discussion:
This project consists of roadway reconstruction of Porter Rd beginning approximately 270' north of Morton Ranch Rd and ends approximately 545' south of Clay Rd. Porter Rd will be reconstructed from an existing two-lane asphalt road with roadside ditches to a four-lane concrete curb and gutter boulevard with storm sewer system, properly sloped driveways. Overall, the project enhances transportation and safety within the project limits and reduces the traffic congestion in Northwest Katy
Expected Impact:
Awarding the contract will allow the recommended bidder to proceed with construction. Project is needed to meet the traffic demand and reduces the traffic congestion in Northwest Katy
Alternative Options:
The alternative is not to award the contract. If no action is taken, the Road widening and associated improvements will not be constructed.
County Strategic Plan Goal: 2. Connect our com...
Click here for full text