File #: 26-3092    Version: 1 Name:
Type: Interlocal Agreement Status: Passed
File created: 5/3/2026 In control: Commissioners Court
On agenda: 5/14/2026 Final action: 5/14/2026
Title: Request for approval of an amendment to an interlocal agreement with Grant Road Public Utility District for the Recovery and Resiliency Division (RRD) Prado Woods Subdivision Drainage Improvements - 2018 project, UPIN 19103MF16N01, Precinct 3.
Sponsors: Mony Hossain
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: Commissioner, Precinct 3
Secondary Department Head/Elected Official: Tom S. Ramsey, P.E., Commissioner

Regular or Supplemental RCA: Regular RCA

Type of Request: Interlocal Agreement

Project ID (if applicable): UPIN 19103MF16N01
Vendor/Entity Legal Name (if applicable): Grant Road Public Utility District

MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: Exempt - Interlocal/Cooperative Agreement

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of an amendment to an interlocal agreement with Grant Road Public Utility District for the Recovery and Resiliency Division (RRD) Prado Woods Subdivision Drainage Improvements - 2018 project, UPIN 19103MF16N01, Precinct 3.
end

Background and Discussion:
The amendment revises the first sentence of Section 1.B(iv)(1) of the agreement and modifies Exhibit A.
This project seeks to reduce flood risk and strengthen resiliency in Harris County by assisting in the alleviation
of structural flood damage to homes in the community. This study report is a step in the process to reduce the
financial, physical, and emotional burden flood damage places on homeowners and will reduce the financial
impact of recovery costs to the Prado Woods subdivision. The scope and proposed improvements consist of
upsizing an existing pump station and enlarging an existing basin.

Expected Impact:
This project seeks to reduce flooding and strengthen resiliency in Harris County by assisting in the alleviation
of structural floods in the Prado Woods subdivision. No impact to project cost, schedule or staffing
anticipated.