Legislation Details

File #: 26-2991    Version: 1 Name:
Type: Discussion Item Status: Passed
File created: 4/30/2026 In control: Commissioners Court
On agenda: 5/14/2026 Final action: 5/14/2026
Title: Request for discussion and possible action for approval to issue a purchase order in an amount not to exceed $343,204.21 to Aramark Facility Services for the LED lighting retrofit of the 7th floor at 701 N San Jacinto (Harris County Detention Facility) under the existing Aramark facilities management contract, with a procurement deadline of the week of May 18, 2026.
Sponsors: Mony Hossain
Attachments: 1. 26-2991- 701 San Jacinto - 7th Floor LED Project Back up documents (002).docx.pdf
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: Sheriff
Secondary Department Head/Elected Official: ED Gonzales

Regular or Supplemental RCA: Regular RCA

Type of Request: Discussion Item

Project ID (if applicable): 701 San Jacinto Maintenance Projects
Vendor/Entity Legal Name (if applicable): Aramark

MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for discussion and possible action for approval to issue a purchase order in an amount not to exceed $343,204.21 to Aramark Facility Services for the LED lighting retrofit of the 7th floor at 701 N San Jacinto (Harris County Detention Facility) under the existing Aramark facilities management contract, with a procurement deadline of the week of May 18, 2026.
end

Background and Discussion:
The 7th floor of 701 N San Jacinto currently operates 1,163 fluorescent light fixtures on a continuous 24/7 fixed-output schedule. These fixtures consume energy at a sustained rate with no dimming controls, contributing materially to the facility's annual electricity cost of $824,818.57 (actual TXU Energy billing, March 2025 through February 2026).

An LED lighting upgrade was first considered in October 2025, when Aramark submitted a full fixture replacement proposal at $1,184,790. That proposal was placed on hold for higher priority projects. In March 2026, Aramark submitted an alternative approach: an LED retrofit that installs new LED kits and bulbs into existing fixture housings in lieu of full fixture replacement. The firm-price retrofit quote of $343,204.21 (dated March 18, 2026).

A financial analysis was ...