Legislation Details

File #: 26-2958    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 4/30/2026 In control: Commissioners Court
On agenda: 5/14/2026 Final action: 5/14/2026
Title: Request for approval of change in contract No. 6 with Allgood Construction Co Inc., for the White Oak Bayou Federal Flood Damage Reduction Project, adding 27 calendar days (White Oak Bayou Watershed, Bond ID C-14, Project ID E100-00-00-E007, Job No. 23/0115, Precinct 1, MWBE Contracted Goal: 26%, MWBE Current Participation: 10.01%).
Primary Department: Flood Control District
Primary Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): E100-00-00-E007
Vendor/Entity Legal Name (if applicable): Allgood Construction Co Inc.

MWBE Contracted Goal (if applicable): 26%
MWBE Current Participation (if applicable): 10.01%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of change in contract No. 6 with Allgood Construction Co Inc., for the White Oak Bayou Federal Flood Damage Reduction Project, adding 27 calendar days (White Oak Bayou Watershed, Bond ID C-14, Project ID E100-00-00-E007, Job No. 23/0115, Precinct 1, MWBE Contracted Goal: 26%, MWBE Current Participation: 10.01%).
end

Background and Discussion:
This change in contract is needed to complete the construction contract for this project. Federal Flood Control
Project Channel Modifications Discrete Segment 104 White Oak Bayou Cole Creek to Hollister Street includes
the installation of approximately 1.65 miles of 10-foot to 12-foot width concrete sidewalk bike trails, concrete
sidewalk pedestrian access paths and wheelchair ramps, and excavation and regrading approximately 4.65 miles of drainage channel, including installation of backslope swales. The purpose of this contract change is to increase the quantities of several pay items that have exceeded current contract amounts, add new pay items needed to complete the work, and reduce quantities for items that are no longer required. The contract change includes no increase to the budget and increase project duration by calendar days.

Expected Impact...

Click here for full text